Overhead cranes—often called bridge cranes—are the quiet workhorses that keep heavy industry moving. This field-tested breakdown takes you behind the scenes of a mega-project crane install. You’ll see structural checks, safety, and QA/QC—all explained in clear, real-world language.
What an Overhead/Bridge Crane Is
An overhead crane rides on parallel runways anchored to a building frame, carrying a trolley-mounted hoist for precise, vertical picks. The system delivers three axes of motion: cross-travel along the bridge.
They’re the backbone of heavy shops and assembly lines, from beam handling to turbine assembly.
Why they matter:
Controlled moves for large, expensive equipment.
Less manual handling, fewer delays.
Lower risk during rigging, lifting, and transport inside facilities.
High throughput with fewer ground obstructions.
What This Install Includes
Runways & rails: runway girders with crane rail and clips.
End trucks: wheel assemblies that ride the rail.
Bridge girder(s): cambered and pre-wired.
Trolley & hoist: cross-travel carriage with lifting unit.
Electrics & controls: VFDs, radio remote, pendant.
Stops, bumpers & safety: end stops, buffers, travel limits.
Depending on capacity and span, the crane might be a single-girder 10-ton unit or a massive double-girder 100-ton system. The installation flow stays similar, with heavier rigs demanding extra controls and sign-offs.
Before the First Bolt
A clean install is mostly planning. Key steps:
Drawings & submittals: Freeze the GA and verify reactions with the structural team.
Permits/JSAs: Job Safety Analysis (JSA) for each lift step.
Runway verification: Check baseplates, grout pads, and anchor torque.
Power readiness: Confirm conductor bars or festoon supports, cable trays, and isolation points.
Staging & laydown: Mark crane components with ID tags.
People & roles: Appoint a lift director, rigger, signaler, and electrical lead.
Tiny survey errors balloon into hours of rework. Spend time here.
Alignment That Saves Your Wheels
Runway alignment is the foundation. Targets and checks:
Straightness & elevation: shim packs under clips to meet tolerance.
Gauge (span) & squareness: Use feeler gauges on splice bars, torque rail clips.
End stops & buffers: Verify clearances for bumpers at both ends.
Conductor system: Mount conductor bars or festoon track parallel to the rail.
Log final numbers basement construction on the ITP sheet. Misalignment shows up as crab angle and hot gearboxes—don’t accept it.
Girder Erection & End Trucks
Rigging plan: Choose spreader bars to keep slings clear of electricals. Taglines for swing control.
Sequence:
Install end trucks at staging height to simplify bridge pick.
For double-girder cranes, lift both girders with a matched raise.
Land the bridge on the end trucks and pin/bolt per GA.
Measure diagonal distances to confirm squareness.
Prior to trolley install, bump-test long-travel motors with temporary power (under permit): confirm limit switch wiring. Lock out after test.
Hoist & Trolley
Trolley installation: Mount wheels, align wheel flanges, set side-clearances.
Hoist reeving: Lubricate wire rope; verify dead-end terminations.
Limits & load devices: Check overload/SLI and emergency stop.
Cross-travel adjustment: Align trolley rails on a double-girder.
Pendant/remote: Install pendant festoon or pair radio receiver; function-test deadman and two-step speed controls.
Grinding noises mean something’s off—stop and inspect. Don’t mask issues with higher VFD ramps.
Power with Discipline
Power supply: Drop leads tagged and strain-relieved.
Drive setup: Enable S-curve profiles for precise positioning.
Interlocks & safety: E-stops, limit switches, anti-collision (if multiple cranes), horn, beacon.
Cable management: Keep loops short, add drip loops where needed.
Commissioning crews love clean labeling and clear folders. Photos of terminations help later troubleshooting.
Trust but Verify
Inspection Test Plan (ITP): Hold/witness points for rail alignment, torque, electrical polarity, limit settings.
Torque logs: Re-check after 24 hours if required.
Level & gauge reports: Attach survey prints.
Motor rotation & phasing: Confirm brake lift timing.
Functional tests: Jog commands, inching speeds, limits, overloads, pendant/remote range.
QA/QC is not paperwork—it’s your warranty in a binder.
Proving the System
Static load test: Hold at mid-span and near end stops; monitor deflection and brake performance.
Dynamic load test: Travel long-run, cross-travel, and hoist at rated speed with test load.
Operational checks: Limit switches trigger reliably; overload trips; horn/beacon function.
Training & handover: Operator basics, daily pre-use checks, rigging do’s & don’ts.
Only after these pass do you hand over the keys.
Applications & Use Cases
Construction & steel erection: placing beams, trusses, and precast.
Oil & gas & power: generator and turbine assembly.
Steel mills & foundries: hot metal handling (with the right duty class).
Warehousing & logistics: bulk material moves with minimal floor traffic.
Floor stays clear, production keeps flowing, and precision goes up.
Safety & Engineering Considerations
Rigging discipline: dedicated signaler and stop-work authority.
Lockout/Tagout: test before touch every time.
Fall protection & edges: scissor lifts and manlifts inspected.
Runway integrity: no cracked welds, correct bolt grades, proper grout.
Duty class selection: overspec when uncertainty exists.
A perfect lift is the one nobody notices because nothing went wrong.
Keep It Rolling
Crab angle/drift: re-check runway gauge and wheel alignment.
Hot gearboxes: misalignment or over-tight brakes.
Rope drum spooling: check fleet angle and sheave alignment.
Pendant lag or dropout: antenna placement for radio; inspect festoon collectors.
Wheel wear & rail pitting: lubrication and alignment issues.
A 10-minute weekly check saves days of downtime later.
Fast Facts
Overhead vs. gantry? Choose per site constraints.
Single vs. double girder? Span and duty class usually decide.
How long does install take? Anything from a couple weeks to a few months.
What’s the duty class? FEM/ISO or CMAA classes define cycles and service—don’t guess; size it right.
Why Watch/Read This
If you’re a civil or mechanical engineer, construction manager, shop supervisor, or just a mega-project fan, this deep dive makes the whole process tangible. You’ll gain a checklist mindset that keeps cranes safe and productive.
Want ready-to-use checklists for runway surveys, torque logs, and load-test plans?
Grab the installer pack so your next crane goes in cleaner, faster, and right the first time. Save it to your site tablet for quick reference.
...
Read more arabic articles...
read more about this products